Project Management

Project Management #

How a project goes from an idea to done: a proposal first, a plan once the proposal is accepted, progress shown on the roadmap as work lands, and the project graduated when it is finished. The owner decides at each step; the skills named below draft, and the owner accepts or changes what they draft.


Principles #

  • An idea is shaped before it is planned. What it is for, what it is not, and the smallest version worth having are written down before any plan or roadmap item exists.
  • Building can start before the plan. A working prototype is welcome while a proposal is being written, and is often how its requirements are found. It is not a commitment to the design.
  • Nothing is decided from a draft. While a proposal is in draft, it opens no ADRs: its questions stay open in the proposal and the requirements until it is accepted.
  • A version is done when its definition of done is met. The definition is written before the version’s work starts and then fixed. A new idea goes to the next version, never into the current one; changing the current one is the owner’s deliberate call, noted with its date.
  • Progress is counted from waypoints, never from hand-kept percentages, and a waypoint is marked done, with its date, in the same commit as the work that reaches it.

The steps #

StepWhat is writtenWhereWith
1. ProposalWhat the idea is for, what it is and is not, the MVP, a rough version cut, open questionsThe project’s own docs if it has a repository (architecture/proposals/), otherwise Architecture here/cd:ideation
2. RequirementsWhat it must do, settled and open, and the cases it must get rightBeside the proposalConversation with the owner
3. PlanVersions, each with a definition of done (v1 the MVP); the roadmap item with its waypoints, and its project plan beneath itRoadmap, roadmap/<area>/<item> and its plan.md/cd:version-planning
4. BuildingWaypoints marked done with their dates; a milestone when a version’s definition of done is met; ADRs, change and incident records as the work calls for themThe roadmap item; the records’ own sectionsroadmap-update
5. ProgressA written account of each month, quarter and yearRoadmap Progress, data/accomplishments//cd:progress-reporting
6. DoneThe project graduates: its plan is archived and an entry writtenCompleted Projectsroadmap-update

1. Proposal #

A proposal is one page, in the voice of the repository it lives in. Its status moves from Draft (being written and reviewed) to Proposal (finished, waiting on the owner’s decision) to Accepted, when the owner accepts it and planning starts, or Declined. A proposal is not part of the decision log; it links to the ADRs written once it is accepted.

A project with a repository of its own keeps its proposal there, beside its code ( eds-inventory’s MVP is one). A project with no repository yet is proposed here.

2. Requirements #

The requirements say what the project must do, plainly, with what is still open listed as questions rather than guessed. Cases it must get right are kept by name, so each becomes a test. A question settled while the proposal is in draft is written into the requirements; it becomes an ADR, if it needs one, once the proposal is accepted.

3. Plan #

Once the proposal is accepted, /cd:version-planning cuts its versions with the owner and writes them into Deevnet’s roadmap: a roadmap item with 3–8 waypoints, the last of each version marked milestone: true, and a project plan beneath it with the versions, their definitions of done, phases and tasks. Only the current version needs a full definition of done; later versions have a goal and a sketch until they become current.

4. Building #

Work is carried out by the usual procedures: Change Management for what it changes on a site, Incident Management for what breaks, and ADRs for the design forks. A waypoint is marked done when the work that reaches it is committed. When a version’s definition of done is met, its milestone is marked done and the next version’s definition of done is written.

5. Progress #

Roadmap Progress is drawn from the waypoints at every build. A day or a week lists the waypoints reached in it. A month, quarter or year shows its written account, drafted by /cd:progress-reporting and reviewed by the owner as a pull request; waypoints reached after an account was written are listed beneath it until it is written again. The period today falls in is marked in progress, with the days left in it.

Two catch-ups keep it current, both on a schedule and both able to run by hand:

LightHeavy
WhenDailyThe 1st of each month
WhatChecks the records against the waypoints, and marks done what a record clearly reaches, with its dayThe light run’s work, then drafts each account that is missing and revises each that has fallen behind, month, quarter and year
Keeps currentThe day and week views, and the waypoints beneath each accountThe written accounts
Uncertain waypointsLeft aloneListed for the owner
Pull requestMerged by itself once its checks passReviewed and merged by the owner
CostSmall: a read of the day’s recordsLarger: every stale account rewritten, and a revised month makes its quarter and year stale

Either run that finds nothing new changes nothing and opens no pull request. Both are /cd:progress-reporting: light, or a plain catch-up for the heavy one.

6. Done #

When every version planned is done, the project graduates: its plan moves to the archive with its waypoints, so Roadmap Progress keeps them; its roadmap item is removed; and an entry is added to Completed Projects.