Project Plan

Core Router Uplift: Project Plan #

The mobile site’s core router is a ZimaBoard 832. It hangs under large transfers: a hard hang during a log store deploy, then recurring re0 watchdog timeouts ( INC-0004). It is replaced by hardware that carries them.

Roadmap item: Core Router Uplift

✓ 0 | ↻ 0 | ⏳ 4 (4 total)

Legend: βœ… Complete | πŸ”„ In Progress | ⏳ Planned


Replacement ⏳ #

  • ⏳ Choose the hardware: the N100 Router Appliance is the candidate under evaluation
  • ⏳ Build it from code and swap it in under a change record, the ZimaBoard kept to put back
  • ⏳ Prove it under load: a multi-gigabyte transfer and a full deploy through it, with no hang and no watchdog timeout
  • ⏳ Close INC-0004