Change Record Template (CHG)

Change Record Template (CHG) #

The shape every change record takes. Copy the skeleton below into a new file, fill it in before the change runs, and complete Outcome after it has run. CHG-0001: Flat Network → VLANs is a worked example of a multi-phase change.


Where it goes #

NumberThe next unused CHG-NNNN, in the order records are opened. Global across years, never reused, and kept even if the change is abandoned. Check Change Records for the last one.
Single-page changecontent/docs/changes/<YYYY>/<NNNN>-<slug>.md
Multi-phase changeA folder content/docs/changes/<YYYY>/<NNNN>-<slug>/. _index.md is the record; numbered phase pages hold the procedure; undo.md holds the undo; optionally troubleshooting.md holds issues and follow-ups. Add bookCollapseSection: true to _index.md.
TitleCHG-NNNN: <What changed>, from the site’s point of view, e.g. “CHG-0001: Flat Network → VLANs”
DateThe header’s Date row: the day execution starts. While the change is still Planned, use the planned date, and move it if the date moves.
WeightNNNN, so records sort by number, as ADRs do
IndexAdd a row to Change Records and to that year’s page

Status #

PlannedIn progressComplete, or Rolled back or Abandoned. A record is never deleted. A change that was abandoned or rolled back is exactly the one worth keeping.


Skeleton #

---
title: "CHG-NNNN: <What changed>"
weight: NNNN
---

# CHG-NNNN: <What changed>

| | |
|---|---|
| **Date** | YYYY-MM-DD — the day execution starts |
| **Change type** | Migration · Upgrade · Configuration · Deployment · Decommission |
| **Classification** | Routine · Structural · Disruptive |
| **Status** | Planned · In progress · Complete · Rolled back · Abandoned |
| **Window** | Planned date and time; then the actual start and end |
| **Site** | |
| **Systems** | Hosts and services touched, by inventory name |
| **Automation** | Collection, playbooks or make targets, and the inventory they run against |
| **Risk** | Low · Medium · High — and the one thing most likely to go wrong |
| **Related changes** | None |
| **Related incidents** | None |
| **Related runbooks** | |

---

## Summary

What is changing and why. What the site is like now, and what it will be like after.

## Goal

The end state that counts as done, as facts a command or a look can confirm:

-

## Scope

**In scope:****Out of scope:**
## Risk and impact

| Risk | Where | Guard |
|---|---|---|
| | | |

## Prerequisites

- [ ] Backups taken: <what, and where they are kept>
- [ ] Console or out-of-band access to <devices on the management path>
- [ ] Vault decrypted, collections built
- [ ] Preflight passes: `<command>`

## Procedure

### Step 1: <name>

What this step does, and whether it is disruptive.

**Run:**

```bash
<command>
```

**Verify:**

1. <observable result>

**Undo:** [Undo Step 1](#undo-step-1)

## Verification

The acceptance criteria for the change as a whole.

## Undo

Steps are backed out in reverse order. Name the point where undo stops being practical.

### Undo Step 1

<how to reverse step 1, or "No undo  <why>">

## Outcome

*Completed after the change has run.*

| When | Steps | What happened |
|---|---|---|
| | | |

### Departures from the plan

-

## Follow-ups

- [ ]

Filling it in #

  • Write Goal before Procedure. If the end state cannot be stated as checkable facts, the change is not ready to plan.
  • Every step gets Run, Verify and Undo, and the undo is written before the change runs. Where there is genuinely no undo, write that down; it marks the point of no return.
  • Take verification from the network, not from Ansible. For the network roles, --check --diff is not a dry run and changed=0 is not proof — see Validation Checklist.
  • Record departures, don’t edit them away. When execution differs from the plan, leave the plan as it was and say what happened under Outcome. The plan and the outcome together are the record.
  • Link the incident in the header table if the change caused one, and link the change from the incident record.
  • Retrospective records — written for a change made before it had a record — say so in a note at the top, name their sources (plan, logs, git), and say “not recorded” where the sources are silent, rather than filling the gap.